| 46 |
Sep 2019 |
ATIN Ferrosilicon and Magnesium |
25,000 tpy FeSi75% Production Plant |
Key Equipment Supply |
| 45 |
Sep 2019 |
ATIN Ferrosilicon and Magnesium |
25,000 tpy FeSi75% Production Plant |
Basic & Detailed Engineering Services, Supervisory Services, Training, Purchasing management |
| 44 |
Jun 2019 |
Sanaie Alloy Nahavand Silice |
5,000 tpy FeSi75% Production Plant |
Key Equipment Supply |
| 43 |
Jun 2019 |
Sanaie Alloy Nahavand Silice |
5,000 tpy FeSi75% Production Plant |
Basic & Detailed Engineering Services, Supervisory Services, Consulting |
| 42 |
May 2017 |
Poyan Gohar Kariman |
12,000 tpy FeSi75% Production Plant |
Basic & Detailed Engineering Services, Supervisory Services |
| 41 |
Oct 2016 |
Asia Steel Metallurgy Ind. |
15,000 tpy FeMn Production Plant |
Basic & Detailed Engineering of Landscaping Services |
| 40 |
Sep 2015 |
Foolad Sang Mining and Industrial |
330,000 tpy Quicklime Production Plant |
International Tender Document for
Lime & Dolo-lime Plant |
| 39 |
Aug 2014 |
Jahangir Gostar Alloy Saveh |
12,000 tpy FeSi75% Production Plant |
Basic & Detailed Engineering Services, Supervisory Services |
| 38 |
Mar 2014 |
Jahan Novin Aria |
H.C. FeCr Project |
Preliminary Evaluations & Studies –Phase 0 |
| 37 |
Oct 2013 |
Iran Ferroalloy Ind. |
Ferrosilicon Production Plant |
Engineering Services for Supply, Manufacturing, Erection & Commissioning of Continuous Casting Machine (Three Strand) |
| 36 |
Jul 2013 |
Iran Ferrosilice |
Modification of Furnace Shell & Refractories |
Basic & Detailed Engineering |
| 35 |
Apr 2013 |
Iran Ferroalloy Ind. |
Silicon Metal & Ferrosilicon Production Line |
Continuous Casting Machine + Mud gun / Drilling Machine |
| 34 |
Dec 2011 |
Asia Steel Metallurgy Ind. |
15,000 tpy FeMn Production Plant |
Complete Engineering Services for the whole Plant |
| 33 |
Apr 2010 |
Sabok Sazan Lowshan |
10,000 tpy Silicon Metal Production Plant |
Basic & Detail Eng. for Auxiliary Buildings |
| 32 |
Sep 2009 |
Sabok Sazan Lowshan |
10,000 tpy Silicon Metal Production Plant |
Engineering Services |
| 31 |
Jul 2009 |
Iran Ferroalloy Ind. |
Silicon Metal & Ferrosilicon Production Line |
Commissioning of Dedusting Plants of Furnaces 2&3 |
| 30 |
Oct 2007 |
Asia Steel Metallurgy Ind. |
HC FeMn Production Plant |
Basic Engineering Services |
| 29 |
Aug 2007 |
IMPASCO |
H.C. FeCr Production Plant |
Procurement of Soderberg Electrode |
| 28 |
Dec 2006 |
Asia Steel Metallurgy Ind. |
H.C. FeMn Project |
Preliminary Evaluations & Studies –Phase 0 |
| 27 |
May 2005 |
Mojtame Farayand Felez |
Aluminum Castings with Lost Foam Process |
Preparation of International Invitation To Bid (ITB) |
| 26 |
Mar 2005 |
IMPASCO |
20 MVA FeCr Plant |
Procurement & Supply of Plant Equipment |
| 25 |
Jun 2004 |
Iran Ferroalloy Ind. |
Silicon Metal & Ferrosilicon Production Lines |
Engineering Services (Basic Engineering & Detail Engineering) for the whole Plants |
| 24 |
Dec 2003 |
Iran Ferroalloy Ind. |
Filter Plant –Microsilica Production Line |
Bag House Filter Optimization by Utilizing Gore-Tex Filter Bags |
| 23 |
Dec 2002 |
IMPASCO |
20 MVA FeCr Plant |
EPC Contract for Water Treatment, Furnace Water Cooling System, Oxygen, Hydraulics & Utilities |
| 22 |
Nov 2002 |
SMS Demag |
39 MVA FeSi Furnace |
Basic & Detail Eng. for Raw Material Handling, Water Cooling System, Casting Equipment, Utility Systems, Furnace and Plant Electrical Systems |
| 21 |
Apr 2001 |
Sabzevar FeCr project |
20 MVA FeCr Plant |
Detail Engineering / Shop Drawing for Locally Manufactured Equipment |
| 20 |
Dec 2000 |
Sabzevar FeCr Project |
20 MVA FeCr Plant |
Engineering Services, Design of Plant (in Cooperation with Pyromet Co. -South Africa) |
| 19 |
May 2000 |
Navid Alyazh |
3.75 MVA FeCr Furnace |
Plant Refurbishment (Electrode Column, High Current Supply Lines & Furnace Lining Design) and Product Change-Over from FeSi to FeCr |
| 18 |
Sep 1999 |
Ministry of Mines & Metals |
4*25000 tpy FeCr Plants |
Negotiation with Foreign Investors (ABB) |
| 17 |
Sep 1999 |
Iran Roy-Gostar |
2 MVA zinc Furnace |
Process Optimization, Concentrate Treatment |
| 16 |
Jun 1999 |
Iran Roy-Gostar |
2 MVA zinc Furnace |
Furnace Lining Design and Plant Commissioning |
| 15 |
Apr 1999 |
Ehya Sanay-e Khorasan |
20000 tpy FeCr Project |
Technical, Economical Consultancy to Absorb Foreign Investors, Proposals Evaluation |
| 14 |
Feb 1999 |
Ministry of Mines & Metals |
FeSiAl Production from High Ash Refuse of Coal Washing Plants |
R&D Research, Process Description |
| 13 |
Dec 1998 |
Qeshm Metal Corp. |
20 MVA FeMn/SiMn Plant |
Design Appraisal, Design Modification, Supervision |
| 12 |
Nov 1998 |
Iran Ferroalloy Ind. |
52.8 MVA FeSi Furnace |
Design, Manufacture & Supply of Quartz Treatment Plant |
| 11 |
Apr 1998 |
Sabzevar FeCr Project |
20 MVA FeCr Plant |
Conceptual Design / Basic Engineering Services |
| 10 |
Mar 1998 |
Ehya Sanay-e Khorasan |
20000 tpy FeCr Project |
Preparation of International Invitation To Bid (ITB) |
| 9 |
Feb 1998 |
Iran Ferrosilice |
55.2 MVA FeSi Furnace |
Training of Key Personal, Furnace Optimization |
| 8 |
Nov 1997 |
Navid Alyazh |
3.75 MVA FeSi Furnace |
Design, Manufacture & Supply of Stoking Machine |
| 7 |
Jul 1997 |
Navid Alyazh |
3.75 MVA FeSi Furnace |
Process Optimization and Trouble Shooting |
| 6 |
Feb 1997 |
Iran Ferrosilice |
55.2 MVA FeSi Furnace |
Design Evaluation, Selection of Raw material, Quartz Mine Evaluation |
| 5 |
Jan 1997 |
Navid Alyazh |
3.75 MVA FeSi Furnace |
Training of Key Personal, Production Supervision |
| 4 |
Dec 1996 |
Iran Ferrosilice |
55.2 MVA FeSi Furnace |
SiC Removal with Wash-out Procedure |
| 3 |
Aug 1996 |
AlMahdi Aluminum |
Anode Making & Anode Rodding Plant |
Process Engineering Services |
| 2 |
Jul 1996 |
Navid Manganese |
13.2 MVA FeMn Furnace |
Design and Existing Equipment Evaluation, Process Technology of FeMn Production |
| 1 |
Jun 1996 |
Navid Alyazh |
3.75 MVA FeSi Furnace |
Plant Overhaul, Furnace Relining and Commissioning |